1.
★ Final term paper (screens, paper 2)Lecture 6

Which of the following give the excess of available time over the activity time when all jobs start as early as possible?

  1. ATotal float
  2. BFree float
  3. CIndependent float
  4. DEarly finish times

Free float = (E_j - E_i) - t_ij, the spare time when all activities start at their earliest times.

2.
★ Final term 2012Lecture 9

Best possible time estimate that a given activity would take under normal conditions which often exist, is called

  1. AMost Likely time estimate
  2. BPessimistic time estimate
  3. CSmallest time estimate
  4. DActivity time estimate

The most likely estimate is the time the activity would take under normal conditions that occur most often.

3.
★ Final term 2012Lecture 9

In PERT, activity time estimates are distributed according to

  1. ABeta Distribution
  2. BNormal Distribution
  3. CPoisson distribution
  4. DBinomial Distribution

PERT assumes each activity's time follows a beta distribution.

4.
★ Final term Fall 2005Lecture 9

Similarity between CPM and PERT is

  1. ABoth are used to plan the scheduling of individual activities that make up a project
  2. BBoth can be used to determine the earliest/latest stat and finish time for each activity
  3. CAll of the above

Both CPM and PERT schedule project activities and give earliest/latest start and finish times.

5.
★ Final term Fall 2006Lecture 13

In purchasing model with shortage, the formula of order size is

  1. AQ* = sqrt(2C2D/C3)
  2. BQ* = sqrt(2C2D/C3) sqrt((C3+C4)/C4)
  3. CQ* = sqrt(2C2D/C3) sqrt(R/(R-D))
  4. DQ* = sqrt(2C2D/(C3(1-D/R))) sqrt((C3+C4)/C4)

With shortages allowed, the basic EOQ is multiplied by sqrt((C3+C4)/C4); terms with R belong to manufacturing models.

6.
★ Final term 2012Lecture 17

In a linear Programming Problem (LPP), which of the following must be hold?

  1. AOnly objective function is linear
  2. BBoth objective function and constraints are linear
  3. COnly constraints needs to be linear
  4. DAt least one of objective function or constraint should be linear

An LP model requires a linear objective function and linear constraints.

7.
★ Final term 2012

For any activity backward pass computations provide its

  1. AEarliest start times
  2. BLatest start times
  3. CModerate start times
  4. DCompletion time

The backward pass from the project end gives each activity's latest finish and latest start times.

8.
★ Final term paper (screens, paper 2)

CPM can help you figure out EXCEPT:

  1. Ahow long your complex project will take to complete
  2. Bwhich activities are "critical," meaning that they have to be done on time or else the whole project will take longer
  3. Cwhat is the most costly way to speed up the project
  4. Dyou can try to speed up the project

CPM looks for the least costly way to crash a project, not the most costly.

9.
★ Final term paper (screens, paper 2)

Early finish time of the event '3' in the following project is -------. Network: 1->3 duration 6; 1->2 duration 3; 2->3 duration 5.

  1. A14 days
  2. B2 days
  3. C8 days
  4. D6 days

Event 3 is reached at max(6, 3+5) = 8 days.

10.
★ Final term paper (screens, paper 2)

If shortage cost is infinity, then ..........

  1. Ano shortages are allowed
  2. Bno inventory carrying cost is allowed
  3. COrdering cost is zero
  4. DPurchase cost = Carrying cost

An infinite shortage cost makes any shortage prohibitively costly, so no shortages occur.

11.
★ Final term Fall 2006

In the following network, the critical path is: Network: A(1-2)=5, B(2-3)=7, C(2-4)=9, D(3-5)=11, F(4-5)=9, E(4-6)=3, G(5-7)=2, H(6-7)=4.

  1. AA - B - D - G
  2. BA - C - E - H
  3. CA - C - F - G
  4. DBoth (a) and (c)

A-B-D-G = 25 and A-C-F-G = 25 are both longest, while A-C-E-H = 21.