Best possible time estimate that a given activity would take under normal conditions which often exist, is called
- AMost Likely time estimate
- BPessimistic time estimate
- CSmallest time estimate
- DActivity time estimate
The most likely estimate is the time the activity would take under normal conditions that occur most often.
In PERT, activity time estimates are distributed according to
- ABeta Distribution
- BNormal Distribution
- CPoisson distribution
- DBinomial Distribution
PERT assumes each activity's time follows a beta distribution.
3.★ Final term Fall 2005
Similarity between CPM and PERT is
- ABoth are used to plan the scheduling of individual activities that make up a project
- BBoth can be used to determine the earliest/latest stat and finish time for each activity
- CAll of the above
Both CPM and PERT schedule project activities and give earliest/latest start and finish times.